Contract Agreement Amount
Rs. 5,87,70,778
Physical Progress
0.00%
Financial Progress
70.07%
Remaining Payment
Rs. 29
Consteruction of Bridge over Yawara khola along Mawadin Nundhaki Road in Sankhuwasabha District.(Prestressed Concrete)
Office: डिभिजन सडक कार्यालय, तुम्लीङटार, संखुवासभा (174)
Fiscal Year: 073-74
Contract Date: 13-Sep-16
Start Date: 28-Sep-16
Completion Date: 30-Mar-2022 (EOT Done)
Project Description
No description available.