Contract Agreement Amount
Rs. 2,81,96,982
Physical Progress
75.00%
Financial Progress
70.02%
Remaining Payment
Rs. 29
Rehabilitation of Hilepani-Okhaldhunga-Mude-Phaplu road section, Okhaldhunga and Solukhumbu
Office: सडक विभाग, काठमाण्डौ (2)
Fiscal Year: 079-80
Contract Date: 6-Feb-23
Start Date: 6-Feb-23
Completion Date: 04-May-2024 (EOT Not Done)