Contract Agreement Amount

Rs. 4,22,28,292

Physical Progress

2.51%

Financial Progress

69.95%

Remaining Payment

Rs. 30

Roadway Improvement Work (Widening, Structures and Pavement Work) - 2nd Pck Along Roadway Improvement Work (Widening, Structures and Pavement Work) - 2nd Pck (RDJML/3370114/078/79-12)

Office: डिभिजन सडक कार्यालय, जुम्ला (179)

Fiscal Year: 078-79

2.51%

Contract Date: 29-Sep-21

Start Date: 29-Sep-21

Completion Date: 09-Feb-2024 (EOT Done)

Project Description

No description available.