Contract Agreement Amount
Rs. 38,14,23,840
Physical Progress
58.00%
Financial Progress
69.81%
Remaining Payment
Rs. 30
Bituminous Pavement work with Structural works from Khadbari(Loving Hill) to Thamserkhu 0+000 to 14+000 km
Office: उत्तर दक्षिण, कोशी सडक योजना, संखुवासभा (57)
Fiscal Year: 077-78
Contract Date: 1-Jul-21
Start Date: 1-Jul-21
Completion Date: 01-Jul-2025 (EOT Done)
Project Description
No description available.