Contract Agreement Amount

Rs. 1,48,26,978

Physical Progress

70.00%

Financial Progress

69.72%

Remaining Payment

Rs. 30

Road improvement works along Mayadevi Gaupalika-8, Siddharthanagar Municipality to Bale Bagiya Connecting Road (from chainage 0+000 to 0+580 m,considering shiva mandir as 0+000) in Rupendehi District.

Office: सडक डिभिजन, वुटवल (28)

Fiscal Year: 076-77

70.00%

Contract Date: 16-Jun-20

Start Date: 16-Jun-20

Completion Date: 13-Apr-2022 (EOT Done)

Project Description

No description available.