Contract Agreement Amount

Rs. 3,68,51,191

Physical Progress

100.00%

Financial Progress

69.57%

Remaining Payment

Rs. 30

Construction of RCC Bridge over Chitaura Khola on Jhalari Pipaladi Municipility-11, Near Bhim Adarsha Primary School, Kanchanpur

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 073-74

100.00%

Contract Date: 28-Apr-17

Start Date: 28-Apr-17

Completion Date: 12-Feb-2020 (EOT Done)