Contract Agreement Amount
Rs. 26,91,85,284
Physical Progress
0.00%
Financial Progress
69.55%
Remaining Payment
Rs. 30
MIDHLDNG3371384/073/074
Office: Puspalal (Midhill) Road Project, Dailekh (277)
Fiscal Year: 073-74
Contract Date: 19-Jun-17
Start Date: 10-Jul-17
Completion Date: 14-May-2023 (EOT Done)
Project Description
No description available.