Contract Agreement Amount

Rs. 2,71,88,802

Physical Progress

0.00%

Financial Progress

69.16%

Remaining Payment

Rs. 30

Rehabilitation of Pavement work in Dulegaunda Kotre Road Section along Prithivi Highway

Office: सडक डिभिजन, तनहुं (25)

Fiscal Year: 072-73

0.00%

Contract Date: 27-Jul-16

Start Date: 28-Jul-16

Completion Date: 29-Oct-2017 (EOT Done)

Project Description

No description available.