Contract Agreement Amount

Rs. 6,40,27,926

Physical Progress

0.00%

Financial Progress

69.07%

Remaining Payment

Rs. 30

Construction of Arunkhola Bridge along Patasa Ramapur Mityal Road, Nawalparasi

Office: सडक डिभिजन, वुटवल (28)

Fiscal Year: 073-74

0.00%

Contract Date: 19-May-17

Start Date: 24-Jun-17

Completion Date: 04-Aug-2019 (EOT Not Done)

Project Description

No description available.