Contract Agreement Amount
Rs. 2,41,37,052
Physical Progress
98.00%
Financial Progress
68.22%
Remaining Payment
Rs. 31
Periodic maintenance on Araniko Highway (LamosanghuBarhabise sector), Sindhupalchowk
Office: डिभिजन सडक कार्यालय, दोलखा (18)
Fiscal Year: 075-76
Contract Date: 5-Mar-19
Start Date: 25-Mar-19
Completion Date: 13-Jun-2019 (EOT Not Done)