Contract Agreement Amount

Rs. 8,71,63,625

Physical Progress

75.00%

Financial Progress

67.86%

Remaining Payment

Rs. 32

Construction of Prestress T-Girder bridge over Madi river along Bhingri-4 Jaluke Nalsi Road

Office: Road Division, Pyuthaan (258)

Fiscal Year: 072-73

75.00%

Contract Date: 28-Apr-16

Start Date: 28-Apr-16

Completion Date: 13-Apr-2023 (EOT Done)

Project Description

No description available.