Contract Agreement Amount
Rs. 3,78,57,795
Physical Progress
71.00%
Financial Progress
67.64%
Remaining Payment
Rs. 32
Construction of Pre-Stressed RCC Bridge over Soram River along Bagdaha-Jayapur Sadak, Sarlahi
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 074-75
Contract Date: 27-Feb-18
Start Date: 27-Feb-18
Completion Date: 13-Apr-2025 (EOT Done)
Project Description
No description available.