Contract Agreement Amount

Rs. 49,01,480

Physical Progress

0.00%

Financial Progress

67.49%

Remaining Payment

Rs. 32

Specific Maintenance of Road Surface in Bitthad-Chainpur Section of Khodpe -Chainpur Highway, Ch: 33+000 to 108+000 (NH-64)

Office: सडक डिभिजन, बैतडी (36)

Fiscal Year: 078-79

0.00%

Contract Date: 29-Oct-21

Start Date: 29-Oct-21

Completion Date: 13-Apr-2022 (EOT Not Done)

Project Description

No description available.