Contract Agreement Amount

Rs. 2,04,46,901

Physical Progress

70.00%

Financial Progress

66.97%

Remaining Payment

Rs. 33

Construction of Bailey Bridge Over Rupgad khola and tirpuracote bheri khola Dolpa

Office: डिभिजन सडक कार्यालय, चौरजहारी (181)

Fiscal Year: 077-78

70.00%

Contract Date: 20-Dec-20

Start Date: 20-Dec-20

Completion Date: 13-Apr-2022 (EOT Done)

Project Description

No description available.