Contract Agreement Amount
Rs. 2,18,87,430
Physical Progress
0.00%
Financial Progress
66.73%
Remaining Payment
Rs. 33
Construction of RCC T-Beam Bridge over Ghatte River at Mahakali Highway, Darchula in Ghatte Khola, Mahakali Highway (Ch. 306+856), Api-15, Darchula
Office: सडक डिभिजन, बैतडी (36)
Fiscal Year: 072-73
Contract Date: 24-Feb-16
Start Date: 24-Feb-16
Completion Date: 25-May-2017 (EOT Not Done)