Contract Agreement Amount
Rs. 3,86,74,971
Physical Progress
0.00%
Financial Progress
66.32%
Remaining Payment
Rs. 33
Roadway excavation and retaining/Breast wall construction,cross-drainage structure construction
Office: Puspalal (Midhill) Road Project, Panchthar (273)
Fiscal Year: 073-74
Contract Date: 18-Sep-17
Start Date: 18-Sep-17
Completion Date: 17-Nov-2021 (EOT Done)
Project Description
No description available.