Contract Agreement Amount

Rs. 3,86,74,971

Physical Progress

0.00%

Financial Progress

66.32%

Remaining Payment

Rs. 33

Roadway excavation and retaining/Breast wall construction,cross-drainage structure construction

Office: Puspalal (Midhill) Road Project, Panchthar (273)

Fiscal Year: 073-74

0.00%

Contract Date: 18-Sep-17

Start Date: 18-Sep-17

Completion Date: 17-Nov-2021 (EOT Done)

Project Description

No description available.