Contract Agreement Amount

Rs. 8,67,40,001

Physical Progress

67.00%

Financial Progress

66.14%

Remaining Payment

Rs. 33

Construction of PSC Girder Bridge (2*35m Span) over Banganga River along Pipara-Bikramsota-Pawara Road

Office: डिभिजन सडक कार्यालय, चितवन (20)

Fiscal Year: 076-77

67.00%

Contract Date: 25-Aug-20

Start Date: 25-Aug-20

Completion Date: 20-Feb-2023 (EOT Not Done)

Project Description

No description available.