Contract Agreement Amount
Rs. 41,42,247
Physical Progress
70.00%
Financial Progress
66.10%
Remaining Payment
Rs. 33
Kusma-Chamarke-Kotgaun-Halhale-Kafaldanda Sadak, Parbat.
Office: Road Division, Baglung (254)
Fiscal Year: 076-77
Contract Date: 14-Jun-20
Start Date: 14-Jun-20
Completion Date: 15-Dec-2020 (EOT Not Done)
Project Description
No description available.