Contract Agreement Amount
Rs. 9,62,04,717
Physical Progress
0.00%
Financial Progress
65.99%
Remaining Payment
Rs. 34
Construction of PSC Bridge over Gangol River , Auraha V.D.C. along Jhakhara-Santhi Road,Parsa.
Office: डिभिजन सडक कार्यालय, मकवानपुर (19)
Fiscal Year: 071-72
Contract Date: 16-Jul-15
Start Date: 17-Jul-15
Completion Date: 15-Jul-2018 (EOT Not Done)
Project Description
No description available.