Contract Agreement Amount
Rs. 3,45,58,528
Physical Progress
98.54%
Financial Progress
65.69%
Remaining Payment
Rs. 34
Rehabilitation Works on Surkhet-Ranimatta Road (Ch. 7+700 to 8+800 & 16+000 to 22+000)
Office: सडक डिभिजन, सुर्खेत (33)
Fiscal Year: 076-77
Contract Date: 3-Mar-20
Start Date: 6-Mar-20
Completion Date: 04-Mar-2021 (EOT Not Done)