Contract Agreement Amount

Rs. 7,37,525

Physical Progress

0.00%

Financial Progress

65.56%

Remaining Payment

Rs. 34

Specific maintenance (Masonary wall construction at Sindhuli ) at Section I & II

Office: सूर्यविनायक-धुलिखेल​, धुलिखेल-सिन्धुली-बर्दिवास सडक आयोजना, काठमाण्डौ (225)

Fiscal Year: 074-75

0.00%

Contract Date: 8-May-18

Start Date: 8-May-18

Completion Date: 11-Oct-2018 (EOT Done)