Contract Agreement Amount
Rs. 26,84,08,209
Physical Progress
64.69%
Financial Progress
65.35%
Remaining Payment
Rs. 34
Road Improvement to Blacktop Standard with necessary structure works at Jorsal-Tamor-Sakranti-Myanglung sector Chainage (77+000-83+000)
Office: Puspalal (Midhill) Road Project, Panchthar (273)
Fiscal Year: 072-73
Contract Date: 17-Mar-16
Start Date: 17-Mar-16
Completion Date: 29-Mar-2023 (EOT Done)
Project Description
No description available.