Contract Agreement Amount

Rs. 11,54,71,357

Physical Progress

62.00%

Financial Progress

65.29%

Remaining Payment

Rs. 34

Maintenance and Safety works on SRN Bridges along MRM and Hulaki Rajmarg (Jhapa-Siraha section)

Office: सडक विभाग, काठमाण्डौ (2)

Fiscal Year: 079-80

62.00%

Contract Date: 26-Jun-23

Start Date: 26-Jun-23

Completion Date: 13-Jun-2024 (EOT Done)

Project Description

No description available.