Contract Agreement Amount
Rs. 11,54,71,357
Physical Progress
62.00%
Financial Progress
65.29%
Remaining Payment
Rs. 34
Maintenance and Safety works on SRN Bridges along MRM and Hulaki Rajmarg (Jhapa-Siraha section)
Office: सडक विभाग, काठमाण्डौ (2)
Fiscal Year: 079-80
Contract Date: 26-Jun-23
Start Date: 26-Jun-23
Completion Date: 13-Jun-2024 (EOT Done)
Project Description
No description available.