Contract Agreement Amount

Rs. 2,95,54,033

Physical Progress

65.00%

Financial Progress

64.84%

Remaining Payment

Rs. 35

Highway upgrading works in Black top standard Surkhet- Tallo Dungeshwor - Satkhamba- Dullu - Pipalkot- khulau - Manma - Nagma- Jumla Sadak ( Tallo Dungeshwor - Dullu Section ) 11+500 to 13+900 ( Naule- Pokhran Section

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 078-79

65.00%

Contract Date: 28-Oct-21

Start Date: 4-Nov-21

Completion Date: 14-Jul-2022 (EOT Not Done)

Project Description

No description available.