Contract Agreement Amount

Rs. 9,62,04,717

Physical Progress

0.00%

Financial Progress

64.38%

Remaining Payment

Rs. 35

Construction of PSC Bridge over Gangol River , Auraha V.D.C. along Jhakhara-Santhi Road,Parsa.

Office: डिभिजन सडक कार्यालय, मकवानपुर (19)

Fiscal Year: 071-72

0.00%

Contract Date: 16-Jul-15

Start Date: 16-Jul-15

Completion Date: 13-Apr-2022 (EOT Done)

Project Description

No description available.