Contract Agreement Amount

Rs. 4,80,20,099

Physical Progress

64.20%

Financial Progress

64.20%

Remaining Payment

Rs. 35

Construction of Hanumante River Bridge ,Along madhayapur Thimi ward no.16 connecting Hanuman Mandir and Imadole

Office: डिभिजन सडक कार्यालय, ललितपुर (23)

Fiscal Year: 077-78

64.20%

Contract Date: 29-Jan-21

Start Date: 29-Jan-21

Completion Date: 29-Jan-2023 (EOT Not Done)

Project Description

No description available.