Contract Agreement Amount
Rs. 1,48,92,117
Physical Progress
100.00%
Financial Progress
63.63%
Remaining Payment
Rs. 36
Construction of RCC Bridge over Geuriya Khola in Postal Road Gaurigunj, Jhapa
Office: डिभिजन सडक कार्यालय, झापा (13)
Fiscal Year: 065-66
Contract Date: 16-Apr-09
Start Date: 16-Apr-09
Completion Date: 13-Mar-2020 (EOT Done)
Project Description
No description available.