Contract Agreement Amount
Rs. 4,84,91,795
Physical Progress
0.00%
Financial Progress
62.73%
Remaining Payment
Rs. 37
Construction of Simply supported, 40 m span cast-in-situ, Pre-Stressed Concrete Bridge, Simle, Dhading
Office: डिभिजन सडक कार्यालय, चितवन (20)
Fiscal Year: 075-76
Contract Date: 13-Sep-18
Start Date: 14-Sep-19
Completion Date: 02-Apr-2021 (EOT Not Done)
Project Description
No description available.