Contract Agreement Amount
Rs. 4,93,86,618
Physical Progress
65.00%
Financial Progress
62.40%
Remaining Payment
Rs. 37
Construction of pre-stressed RCC motorable bridge over Jhupra Khola joining Birendranagar Municipality-13 and Satakhani-7, Bhangari, Surkhet
Office: सडक डिभिजन, सुर्खेत (33)
Fiscal Year: 073-74
Contract Date: 7-Sep-17
Start Date: 8-Sep-17
Completion Date: 14-May-2019 (EOT Not Done)
Project Description
No description available.