Contract Agreement Amount

Rs. 4,93,86,618

Physical Progress

65.00%

Financial Progress

62.40%

Remaining Payment

Rs. 37

Construction of pre-stressed RCC motorable bridge over Jhupra Khola joining Birendranagar Municipality-13 and Satakhani-7, Bhangari, Surkhet

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 073-74

65.00%

Contract Date: 7-Sep-17

Start Date: 8-Sep-17

Completion Date: 14-May-2019 (EOT Not Done)

Project Description

No description available.