Contract Agreement Amount
Rs. 95,86,726
Physical Progress
0.00%
Financial Progress
61.59%
Remaining Payment
Rs. 38
E/W, Hume pipe and RCC works along Ghodghas-Nim Chauk-Thalighat-Akraharghat sadak (NH22)
Office: डिभिजन सडक कार्यालय, धनुषा (17)
Fiscal Year: 076-77
Contract Date: 5-Jul-20
Start Date: 5-Jul-20
Completion Date: 12-Apr-2021 (EOT Not Done)
Project Description
No description available.