Contract Agreement Amount
Rs. 24,36,15,323
Physical Progress
62.00%
Financial Progress
61.43%
Remaining Payment
Rs. 38
Shivapuri Ga Pa 7 Sunkhani Dhalanghar Syalping khola Bhanjyang Shivalaya Panchakanya Ga.Pa.3 Ghalebhanjyang Kulkule Thakuri Tole Bhaynle Dupcheshwor Ga.Pa. Samundratar Road, Nuwakot
Office: उत्तर दक्षिण, कोशी सडक योजना, संखुवासभा (57)
Fiscal Year: 078-79
Contract Date: 24-Jun-22
Start Date: 24-Jun-22
Completion Date: 23-Jun-2025 (EOT Not Done)
Project Description
No description available.