Contract Agreement Amount

Rs. 29,01,37,956

Physical Progress

0.00%

Financial Progress

61.34%

Remaining Payment

Rs. 38

Road improvement to blacktop standard with necessary structural work

Office: Puspalal (Midhill) Road Project, Panchthar (273)

Fiscal Year: 072-73

0.00%

Contract Date: 10-Mar-16

Start Date: 10-Mar-16

Completion Date: 28-May-2020 (EOT Done)

Project Description

No description available.