Contract Agreement Amount

Rs. 7,05,68,402

Physical Progress

70.00%

Financial Progress

60.85%

Remaining Payment

Rs. 39

Construction of RCC Bridge over Kamikatte khola on Bhi.Na.Pa. ward no 9 Siddanath mandir near Khola Dovan , Kanchanpur

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 073-74

70.00%

Contract Date: 21-May-17

Start Date: 21-May-17

Completion Date: 30-Jul-2021 (EOT Done)

Project Description

No description available.