Contract Agreement Amount

Rs. 3,22,96,775

Physical Progress

0.00%

Financial Progress

60.60%

Remaining Payment

Rs. 39

Roadway Excavation at Chasada Bhir Section, Humla

Office: हिल्सा सिमिकोट सडक योजना, हुम्ला (217)

Fiscal Year: 072-73

0.00%

Contract Date: 26-Nov-15

Start Date: 26-Nov-15

Completion Date: 13-Apr-2022 (EOT Done)

Project Description

No description available.