Contract Agreement Amount

Rs. 5,15,11,071

Physical Progress

52.50%

Financial Progress

60.45%

Remaining Payment

Rs. 39

Construction of Masonry and Gabion Retaining Structure, Curve and grade improvement and blacktop works on Mirchaiya (Ma. Ra. Ma.) - Katari - Ghurmi Sadak, Siraha and Udayapur, 12+000 - 14+000 & 16+000 - 17+500

Office: हेभिईक्युपमेन्ट डिभिजन, वांके (41)

Fiscal Year: 076-77

52.50%

Contract Date: 10-Jul-20

Start Date: 10-Jul-20

Completion Date: 13-Jun-2021 (EOT Not Done)

Project Description

No description available.