Contract Agreement Amount

Rs. 8,45,31,198

Physical Progress

0.00%

Financial Progress

60.20%

Remaining Payment

Rs. 39

Prestressed Concrete Bridge (2x40m) Construction with Pile Foundation Over Sorahi Khola Along Jodhpur-Badalpur-Sohariya Road, Bardiya

Office: सडक डिभिजन, वांके (32)

Fiscal Year: 073-74

0.00%

Contract Date: 12-Jul-17

Start Date: 12-Jul-17

Completion Date: 12-Dec-2022 (EOT Done)

Project Description

No description available.