Contract Agreement Amount

Rs. 19,60,99,153

Physical Progress

0.00%

Financial Progress

59.94%

Remaining Payment

Rs. 40

Upgrading/ Improvement Works of Hanumannagar Chowk-Rampur-Baharwa-Akaura-Bhadariya, Jaleshwor-Sungha-Matihani-Tulsyahi-Baheda Bela Section of Janakpur Parikrama Road

Office: Janakpur Parikrama, Byparik Margha Bistaar Yojana (Jatahi-Janakpur), Mahottari (232)

Fiscal Year: 070-71

0.00%

Contract Date: 23-Aug-15

Start Date: 13-Jan-17

Completion Date: 13-Apr-2022 (EOT Done)

Project Description

No description available.