Contract Agreement Amount
Rs. 6,15,350
Physical Progress
0.00%
Financial Progress
59.70%
Remaining Payment
Rs. 40
Roadway Excavation and Construction Of Structure on Kusemuse -Chakhure-Pere - Dolphu Gau Sadak,Gugu (DROJML/33701137/077/078-08)
Office: डिभिजन सडक कार्यालय, जुम्ला (179)
Fiscal Year: 077-78
Contract Date: 9-Dec-20
Start Date: 15-Dec-20
Completion Date: 19-Apr-2021 (EOT Not Done)
Project Description
No description available.