Contract Agreement Amount

Rs. 4,69,65,093

Physical Progress

60.00%

Financial Progress

58.94%

Remaining Payment

Rs. 41

Construction of Blacktop works, Masonary Drain and Retaining structures at Mirchaiya (Ma.Ra.Ma.) - Katari - Ghurmi Sadak (Mirchaiya-Katari Section_Package_1) - Chainage 17+100 to 22+100.

Office: ओखलढुङगा सल्लेरी सडक योजना, सोलुखुम्वु (59)

Fiscal Year: 077-78

60.00%

Contract Date: 18-Apr-21

Start Date: 18-Apr-21

Completion Date: 11-Nov-2023 (EOT Done)

Project Description

No description available.