Contract Agreement Amount
Rs. 4,06,70,678
Physical Progress
75.00%
Financial Progress
58.77%
Remaining Payment
Rs. 41
Construction of 25m Simply Supported Span, Cast-in-situ, 2-Webbed Reinforced Concrete Slab-Deck Bridge Over Kandebhir (Fusre) Khola, Nawalparasi (Chainage 55+900)
Office: योजना तथा अनुगमन महाशाखा (सडक सुरक्षा तथा ट्राफिक शाखा) (5)
Fiscal Year: 078-79
Contract Date: 4-Sep-22
Start Date: 4-Sep-22
Completion Date: 28-Apr-2024 (EOT Not Done)