Contract Agreement Amount
Rs. 89,55,102
Physical Progress
60.00%
Financial Progress
58.30%
Remaining Payment
Rs. 41
Structural, Drainage, and Bituminous work on Chidya khola- Bartumg Road section
Office: सडक डिभिजन, पाल्पा (27)
Fiscal Year: 078-79
Contract Date: 22-Feb-22
Start Date: 8-Mar-22
Completion Date: 08-Mar-2022 (EOT Not Done)
Project Description
No description available.