Contract Agreement Amount
Rs. 25,96,25,763
Physical Progress
60.00%
Financial Progress
58.22%
Remaining Payment
Rs. 41
Damak Chakrapath
Office: डिभिजन सडक कार्यालय, झापा (13)
Fiscal Year: 076-77
Contract Date: 19-Jan-21
Start Date: 19-Jan-21
Completion Date: 19-Jan-2023 (EOT Not Done)
Project Description