Contract Agreement Amount
Rs. 6,12,77,724
Physical Progress
48.00%
Financial Progress
57.93%
Remaining Payment
Rs. 42
Construction of Pre-Stressed RCC Bridge Over Lamaha River Bridge along Harsaha Chowk on Chandranigahpur-Gaur Road (Simara Bhawanipur VDC ward no. 4 Partapur Paltuwa VDC Ward no 9) Rautahat
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 073-74
Contract Date: 3-Apr-17
Start Date: 3-Apr-17
Completion Date: 15-Jul-2023 (EOT Done)
Project Description
No description available.