Contract Agreement Amount

Rs. 6,12,77,724

Physical Progress

48.00%

Financial Progress

57.93%

Remaining Payment

Rs. 42

Construction of Pre-Stressed RCC Bridge Over Lamaha River Bridge along Harsaha Chowk on Chandranigahpur-Gaur Road (Simara Bhawanipur VDC ward no. 4 Partapur Paltuwa VDC Ward no 9) Rautahat

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 073-74

48.00%

Contract Date: 3-Apr-17

Start Date: 3-Apr-17

Completion Date: 15-Jul-2023 (EOT Done)

Project Description

No description available.