Contract Agreement Amount

Rs. 72,27,910

Physical Progress

20.00%

Financial Progress

57.51%

Remaining Payment

Rs. 42

Highway Upgrading and Rehabilitation Works along Rapti Highway Shitalpati- Musikot Road (Kharibot - Bangelakhuri) in Salyan District.

Office: सडक डिभिजन, दाङ्ग (31)

Fiscal Year: 078-79

20.00%

Contract Date: 22-Nov-21

Start Date: 6-Dec-21

Completion Date: 14-May-2023 (EOT Done)

Project Description

No description available.