Contract Agreement Amount
Rs. 72,27,910
Physical Progress
20.00%
Financial Progress
57.51%
Remaining Payment
Rs. 42
Highway Upgrading and Rehabilitation Works along Rapti Highway Shitalpati- Musikot Road (Kharibot - Bangelakhuri) in Salyan District.
Office: सडक डिभिजन, दाङ्ग (31)
Fiscal Year: 078-79
Contract Date: 22-Nov-21
Start Date: 6-Dec-21
Completion Date: 14-May-2023 (EOT Done)