Contract Agreement Amount

Rs. 1,24,10,734

Physical Progress

56.87%

Financial Progress

56.87%

Remaining Payment

Rs. 43

Blacktopped Road Construction Works Including Drainage Structures along Ratuwamai Na.pa.6 Budhbare Bajar Om Kareshwar Shiv Mandir Shibalaya Chowk Ananta Chowk Sanischare Bajar, Morang

Office: Unknown (97)

Fiscal Year: 076-77

56.87%

Contract Date: 27-Jul-20

Start Date: 27-Jul-20

Completion Date: 12-Apr-2021 (EOT Not Done)

Project Description

No description available.