Contract Agreement Amount
Rs. 11,08,57,259
Physical Progress
0.00%
Financial Progress
56.64%
Remaining Payment
Rs. 43
Construction of Prestressed RCC Bridge (Krishnaghat Bridge) over Madi Khola, Madibesi Kalyang, Kaski
Office: सडक डिभिजन, पोखरा (26)
Fiscal Year: 071-72
Contract Date: 13-Oct-15
Start Date: 13-Oct-15
Completion Date: 13-Jun-2019 (EOT Not Done)