Contract Agreement Amount
Rs. 8,63,70,345
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Amar/Shibako/Pushpanjali JV
Office: डिभिजन सडक कार्यालय, सिराहा (16)
Fiscal Year: 077-78
Contract Date: 23-Dec-20
Start Date: 23-Dec-20
Completion Date: 22-Jan-2024 (EOT Not Done)