Contract Agreement Amount

Rs. 2,96,62,195

Physical Progress

56.50%

Financial Progress

56.50%

Remaining Payment

Rs. 43

Construction Of RCC Multi Cell Box Bridge (3x10*x5) Over Rupni Khola Magarthana (RDJKR/33701132/077-78/48)

Office: डिभिजन सडक कार्यालय, धनुषा (17)

Fiscal Year: 078-79

56.50%

Contract Date: 3-Nov-21

Start Date: 3-Nov-21

Completion Date: 02-Nov-2022 (EOT Not Done)

Project Description

No description available.