Contract Agreement Amount
Rs. 30,16,83,600
Physical Progress
60.00%
Financial Progress
55.99%
Remaining Payment
Rs. 44
Construction of Pre-stressed RCC Bridge over Kankai (19 No*38.1 m Span, Total Length 724.8 m), along Bhadrapur-Ratuwa, Hulaki Road, Jhapa
Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, सुनसरी (64)
Fiscal Year: 067-68
Contract Date: 14-Jun-11
Start Date: 14-Jun-11
Completion Date: 14-Jul-2024 (EOT Done)
Project Description
No description available.