Contract Agreement Amount
Rs. 3,13,41,518
Physical Progress
50.00%
Financial Progress
55.83%
Remaining Payment
Rs. 44
राप्ती राजमार्ग अमेलिया तुलसीपुर- सितलपाटी सडक खण्ड
Office: सडक डिभिजन, दाङ्ग (31)
Fiscal Year: 077-78
Contract Date: 23-May-21
Start Date: 23-May-21
Completion Date: 13-Jan-2023 (EOT Done)
Project Description
No description available.